| Credits | |
|---|---|
| Client | Qatar Airways Executive Jet Hangar |
| Main Contractor | Clearspan Technology Middle – East |
| Steel Sub Contractor | Sunrise Steel Workshop, Dubai |
| Consultant | Atkins |
| Scope | Erection and finishing of Structural & Secondary steels |
| Contract Value | 900,000 |
| Project Duration | 2009 November – 2010 July |
| Information | |
| ► State of the art for Qatar Airways. | |
| ► Erection of 500 Tons of structural & Secondary Steel. |
| Credits | ||
|---|---|---|
| Client | New Doha International Airport (NDIA) | |
| Main Contractor | Zubilin | |
| Consultant | Parsons International | |
| Steel Contractor | Ungar Steel | |
| Steel Sub Contractor | Sunrise Steel Workshop, Dubai | |
| Scope | Erection of 2500 Tons of structural steel & Secondary steel | |
| Contract Value | 2 Million | |
| Project Duration | 2011 December – 2012 August | |
| Credits | ||
|---|---|---|
| Client | Milaha (Qatar Navigation) | |
| Main Contractor | Clearspan Technology Middle – East | |
| Consultant | Qatar Design Consortium | |
| Steel Contractor | Sunrise Steel Workshop, Dubai | |
| Scope | Design, Supply, Fabrication and Installation of Steel Structure including Mezzanine Decking wall and Roof Sheet with Sandwich Panel. (450 tons) | |
| Contract Value | 5.4 Million | |
| Project Duration | 2013 April – 2014 January | |
| Credits | ||
|---|---|---|
| Client | Petrotec | |
| Main Contractor | Prosperous Qatar W.L.L | |
| Consultant | Qatar Design Consortium | |
| Steel Contractor | Sunrise Steel Workshop, Dubai | |
| Scope | Installation of Structural Steel Roofing and Wall Cladding 5000 Sq.mtrs | |
| Contract Value | 550,000 | |
| Project Duration | 2014 January – 2014 May | |
| Credits | ||
|---|---|---|
| Client | Milaha | |
| Main Contractor | Sunrise Steel Workshop, Dubai | |
| Consultant | Qatar Design Consortium | |
| Scope | Miscellaneous and Tie - in Works of High Voltage and Telecom and Water Supply Network as per Raslaffan guide lines | |
| Contract Value | 2.4 Million | |
| Project Duration | 2014 October – 2015 Feb | |
| Credits | ||
|---|---|---|
| Client | AKD | |
| Main Contractor | Sunrise Steel Workshop, Dubai | |
| Consultant | Qatar Design Consortium | |
| Steel Contractor | Sunrise Steel Workshop, Dubai | |
| Scope | Punch List Items | |
| Contract Value | 750,000 | |
| Project Duration | 2015 June – 2015 August |
| Credits | ||
|---|---|---|
| Client | Ashghal | |
| Main Contractor | Hyundai Engineering and Construction | |
| Consultant | CDM Smith | |
| Steel Contractor | Sunrise Steel Workshop, Dubai | |
| Scope | Concrete for Temporary Towers 2,700 cubic meters of concrete and 250 tons of steel including laying dismantling and reinstatement of the area | |
| Contract Value | 4.95 Million | |
| Project Duration | 2015 December – 2016 April |
| Credits | ||
|---|---|---|
| Client | Qatar University | |
| Main Contractor | Al Dharwish Engineering | |
| Consultant | Dar Al Handasa | |
| Steel Contractor | Alimoosa & Sons | |
| Steel Sub Contractor | Sunrise Steel Workshop, Dubai | |
| Scope | Installation of Main and Secondary Steel for various Buildings | |
| Contract Value | 850,000 | |
| Project Duration | 2016 April – 2017 March |